Transit expansion in metro Atlanta will continue in Atlanta and Clayton County. The region will go without eye-popping transit projects once envisioned in Gwinnett and DeKalb counties, nor will Newton County pilot a transit system, in the foreseeable future.

Summerhill, Turner Field, Georgia State
The Summerhill neighborhood that’s home to Georgia State’s Center Parc Stadium is to be served by a bus rapid transit line that is to terminate near MARTA’s Five Points Station. Credit: Kelly Jordan
The Summerhill neighborhood that’s home to Georgia State’s Center Parc Stadium is to be served by a bus rapid transit line that is to terminate near MARTA’s Five Points Station. Credit: Kelly Jordan

The two ongoing transit projects include:

  • In Downtown Atlanta, building the Summerhill bus rapid transit route;
  • In Clayton County, expanding facilities at the first transit hub in Clayton, at the Clayton Justice Center Transit Hub, and ongoing installation of bus stop amenities throughout the county.

Two major initiatives that are not going forward were either rejected by voters or not put on the ballot. In addition, Newton County voters rejected a transit proposal that received scant attention outside the county:

  • Gwinnett voters rejected a plan to extend heavy rail into their county. The rejection means there are no plans to increase transit to and from a county on track to have the region’s largest population, of a projected 1.48 million residents by 2050, according to the Atlanta Regional Commission. The rail line was part of a $12.2 billion, 30-year proposal;
  • DeKalb County’s Board of Commissioners chose to not seek voter approval of funding for a long-discussed rail line to serve the dense cluster of development at Emory University and the Centers for Disease Control and Prevention. The route was in a transit package the board approved in July 2019, and which many had expected to be added to the Nov. 3 ballot;
  • Newton County voters turned down a pilot transit service. It amounted to $2 million in a $56 transportation program that was to be funded with a 1% sales tax for five years.

MARTA is actively working on the projects in Atlanta and Clayton County.

The Emmaus House and the adjacent chapel, a parish of the Episcopal Diocese of Atlanta, are to be a short distance from a bus rapid transit system to link Summerhill with the Five Points area. Credit: Kelly Jordan

On Thursday, an update on the Summerhill project is slated to include a presentation on the route and station locations, followed by a question/answer session. The virtual meeting is scheduled from 6:30 p.m. to 7:30 p.m. Details and registration information are available here.

The route is required to open by August 2024 and construction must begin by August 2022, according to terms of a federal grant helping to fund the project. MARTA is seeking a consultant to oversee final engineering and design. The deadline for submissions was Nov. 13. No award date appeared to be cited in the Request for Expressions of Interest.

In Clayton County, the focus is on improving the rider experience while waiting for a bus. MARTA is on schedule to install 30 bus stop amenities this year, and 30 additional bus stop amenities are to be completed in 2021. This is the immediate aim of MARTA’s plan to address 150 bus stop amenities over a 5-year period, according to a Sept. 26 virtual update on the Clayton County efforts.

Clayton County transit hub
Clayton County’s first transit hub opened this summer, at the Clayton Justice Center, and MARTA is scheduled to expand it by 2023 with permanent shelters, barriers, digital signage and a Breeze card machine. Credit: MARTA
Clayton County’s first transit hub opened this summer, at the Clayton Justice Center, and MARTA is scheduled to expand it by 2023 with permanent shelters, barriers, digital signage and a Breeze card machine. Credit: MARTA

The installation of such amenities is not always a simple process, according to a presentation by Frank Rucker, MARTA’s chief of planning, programs and innovation. Rucker said challenges include:

  • Gaining support from disinterested property owners and issues with a site that can’t be overcome;
  • Slow permitting time from the Georgia Department of Transportation.

Around the country, voters approved 15 of 18 transit initiatives on the Nov. 3 ballot, according to a report of final ballot counts in the trade publication masstransitmag.com. Georgia accounted for two of the three failed initiatives. Portland voters rejected a payroll tax on employers to provide for a $7 billion toward the TriMet Southwest Corridor Light Rail Project.

David Pendered, Managing Editor, is an Atlanta journalist with more than 30 years experience reporting on the region’s urban affairs, from Atlanta City Hall to the state Capitol. Since 2008, he has written...

Leave a comment

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.